A project with a budget of $200 is half complete (it has earned half its value), but spent $500 so far.
Using the planned value method, calculate the EAC for this project.
A project expected to take 20 weeks has an SPI of 0.8 after 10 weeks.
Assuming progress continues at this rate, what will be its estimate to complete (from today)?
If you calculate a new EAC for the project, what should you do next?