0 of 4 Questions completed
Questions:
Ready to test your new knowledge?
Be sure to choose the response that best answers each question.
If you pass all the quizzes at 100%, you’re eligible to be entered into our Order of Merit.
Good luck!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 4 questions answered correctly
Your time:
Time has elapsed
0 0 Your score: 0
Passing score: 70%
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
What is the formula used to calculate a project’s cost variance?
What is the formula used to calculate a project’s schedule variance?
The planned value of the cookie project at the end of the first hour is $10
The earned value of the cookie project at the end of the first hour is $7.50
The actual cost of the cookie project at the end of the first hour is $9
What is the current cost variance on this project?
The planned value of the cookie project at the end of the first hour is $10
The earned value of the cookie project at the end of the first hour is $7.50
The actual cost of the cookie project at the end of the first hour is $9
What is the current schedule variance on this project?